Building log

06-Sep-2006
Left tank
Catégorie: Wings : Fuel tanks

Some small work on the left tank, this one is equipped for aerobatics. So the first task is to build as small trap door for the second rib, this doors closes so as to trap the fuel in the first bay where the fule pick-up is.



The fuel pickup fittings goes through the angle fabricated yesterday. The rivets have to be positionned carefully so as to be able to tighten the nut.



Here the end result. I still have to install the fuel senders and the inspection hole cover.




Working time on this subpart
Today :  3h (Total : 8h)